How WEM Works... WEM Review Process To submit a claim for review, please send the following:
Submit claim information to claimsservices@skyetec.com WEM Step-by-Step Step 2: If the initial review shows a cost differential of $500 or more, LTS will contact the
mitigation vendor to request drying logs for a detailed re-evaluation of the claim. Equipment used and project readings will be entered into WEM for this reevaluation
of the mitigation vendor’s drying process. The deliverable from this step
will be the Cost Evaluation w/ Drying Logs. Turnaround time for this step will
depend on the mitigation vendor’s expedience in submitting drying logs to LTS.
Step 3: Should the cost differential remain over $500, LTS will proceed with the Agreed Cost
Discussion. An Agreed Cost Discussion Form will be completed to detail
any reduction in the estimate/invoice amount and the parties involved in the
discussion. Like Step 2, the turnaround time for this step will vary dependent upon
the availability of the mitigation vendor. If a mitigation vendor refuses to enter into
the Agreed Cost Discussion, there will be no charge to the carrier.
| |||||||||||||||||
|
|||||||||||||||||